DITA 1.3 Errata 02 schedule

Date

Milestone

Responsible party

Dependencies

Actual date completed

04 December 2017

Build draft DITA 1.3 Errata 02 document (new aggregated format) for TC review

Eberlein

04 Dec 2017

04-08 December 2017

Complete schedule with estimated dates from OASIS

Eberlein

Response from OASIS

07 Dec 2017

11-12 December 2017

Build DITA 1.3 Plus Errata 02 -- All except Errata 02 document (2 days)

Thomas

13-15 December 2017

TC volunteer reviews package for OASIS URLs, cover page info, footers; etc.; package updated if necessary (3 days)

Harrison

19 December 2017

11-15 December 2017
09-15 Jan 2018

Internal TC (DITAweb) review of Errata 02 document (5 days)

All voting TC members

18 December 2017
16 Jan 2018

Editors apply changes to Errata 02 document; add to DITA 1.3 Plus Errata 02 package in Kavi (1 day)

Editors

19 December 2017
16 Jan 2018

Adopt updated Errata 02 document and DITA 1.3 Plus Errata 02 as a Committee Draft Specification; request 15-day public review

DITA TC

20 Dec 2017 - 02 Jan 2018

OASIS staff prepares materials for 15-day public review

OASIS staff

03-18 January 2018

15-day public review

19-22 Jan 2017

Editors respond to 15-day public review comments (2 days)

Editors

23 January 2017

TC approves DITA 1.3 Plus Errata 02

DITA TC

24-30 Jan 2017

OASIS staff prepare DITA 1.3 errata for publication (5 days)

OASIS staff

31 Jan 2017

TC Admin announces DITA 1.3 errata |Chet Ensign|

DITA-1.3-errata-02-schedule (last edited 2018-01-09 17:53:05 by kjeberlein)