Date

Milestone

Dependencies

Date completed

5 July 2016

Test current build process. Does it meet file naming requirements as noted by Chet?

Waiting on info from Chet; info received 11 July 2016

15 July 2016

Test work on content model generation

15 July 2015

29 July 2016

Complete work on content model generation

5 July 2016

29 July 2016

Complete work on SEO and Google analytics

29 July 2016

1-5 August 2016

Build draft DITA 1.3 errata for TC review

8-12 August 2016

Internal TC (DITAweb) review of errata (5 days)

15-19 August 2016

Build Committee Draft Specification (5 days)

23 August 2016

Adopt corrections (and updated spec) as a Committee Draft Specification; request 15-day public review

30 August 2016

23 Aug - 5 Sep 2016

OASIS staff prepares materials for 15-day public review (14 days)

5 October 2016

6-20 Sep 2016
6-20 Oct 2016

15-day public review

21-26 Sep 2016
21 Oct 2016

Editors respond to 15-day public review comments (1 days)

21 October 2016

27 Sep 2016
25 October 2016

TC approves DITA 1.3 errata

25 October 2016

27 Sep - 14 Oct 2016
26 Oct - 9 Nov 2016

OASIS staff prepare DITA 1.3 errata for publication (14 days)

Monday, 17 October 2016
10 Nov 2016

TC Admin announces DITA 1.3 errata